Bio-leaching of low-grade large porphyry chalcopyrite-containing ore
邱冠周1,胡岳华1,王军2,钟康年3
(1.Department of Mineral Engineering, Central South University of Technology, Changsha410083,P.R.China2..Center of Environmental Sciences, Beijing University, Beijing100871,P.R. China3.Wuhan Institute of Chemical Technology, Wuhan 430073,P.R. China)
Abstract: In order to economically recover the copper from the low grade copper ores, a bioleaching solvent extraction electrowinning plant with a design capacity of 2 000 t cathode copper per year in Dexing Copper Mine was operated in September, 1997. The results during the 10 month period of the industrial copper dump leaching have been obtained and the approaches have been carried out to enhance the copper dissolution from the waste rocks. The overall operation flowsheet is depicted. The problems confronted in the process and possible way for improving are discussed.
Key words: low-grade copper ores; bacterial leaching; solvent extraction; electrowinning
Superintended by The China Association for Science and Technology (CAST)
Sponsored by The Nonferrous Metals Society of China (NFSOC)
Managed by Central South University (CSU) 湘ICP备09001153号-9